BACKGROUND: The City’s 2021 Watershed Management Plan is designed to significantly reduce Lake Decatur sedimentation and improve the lake’s water quality through watershed conservation. City staff manages the watershed conservation efforts in-house with the assistance of Northwater Consulting, the City’s Watershed Management Plan consultant.
The waterway to be constructed on private farmland is expected to result in these reductions over the life of the project:
Nitrogen 8,955 pounds
Phosphorus 1,165.5 pounds
Sediment 1,022.4 tons
The agreement financials are:
Owner Cost $ 4,349.00
Maximum City Cost (reimbursed to owner after construction)* $43,055.10
Total Not to Exceed Project Cost $47,839.00
*In order to successfully entice landowners to construct these watershed conservation projects, landowners are reimbursed by the City for 90% of the total project cost. Landowners pay for 10% of the total.
A project summary with location map is attached.
LEGAL REVIEW:
The agreement form was approved by the Legal Department on September 21, 2022.