Item Coversheet
Public Works

DATE:

4/8/2024

MEMO:

2024-52

TO:

Honorable Mayor Julie Moore Wolfe and City Council Members

FROM:
Scot Wrighton, City Manager
Matt Newell, P.E., Public Works Director
Keith Alexander, Water Production Manager
Jennifer Gunter, Watershed and Lake Manager
 

SUBJECT:  Resolution Authorizing Lake Decatur Watershed Protection Program Agreement for West Waterway Improvements with Lynn Clarkson 
SUMMARY RECOMMENDATION:  

It is recommended that the City Council authorize a Lake Decatur Watershed Protection Program Agreement between the City of Decatur and Lynn Clarkson for the construction of a west waterway to control nutrients, sediment and erosion for a not to exceed cost to the City of $49,529.70.  This amount represents 90% of the total project cost of $50,030 with a 10% contingency on the overall project. The remainder ($5,003) will be paid by the property owner.

 

COUNCIL PRIORITY GOALS:
This project addresses City Council’s Priority Goal #6, Key Implementation Strategy #3: Implement recommendations of a Lake Management Plan so that the quantity of sediment, silt and nitrates entering Lake Decatur is significantly reduced, and adopt other strategies designed to assure good water quality and proper watershed stewardship for the future.

 

 
BACKGROUND:  

The City’s 2021 Watershed Management Plan is designed to significantly reduce Lake Decatur sedimentation and improve the lake’s water quality through watershed conservation.  City staff manages the watershed conservation efforts in-house with the assistance of Northwater Consulting, the City’s Watershed Management Plan consultant.

The waterway is to be constructed on private farmland and is expected to result in these reductions over the life of the project: 
Nitrogen 5,970 pounds
Phosphorus 778.5 pounds
Sediment 672.6 tons

The agreement financials are:
Owner Cost $  5,003.00
Maximum City Cost (reimbursed to owner after construction)* $49,529.70
Total Not to Exceed Project Cost $55,033.00

*In order to successfully entice landowners to construct these watershed conservation projects, landowners are reimbursed by the City for 90% of the total project cost.  Landowners pay for 10% of the total.

A project summary with location map is attached.

 

LEGAL REVIEW:
The agreement form was approved by the Legal Department on September 21, 2022.

 

 

 
 
 
PRIOR COUNCIL ACTION:  None. 
POTENTIAL OBJECTIONS:  None foreseen. 
INPUT FROM OTHER SOURCES:  None. 
STAFF REFERENCE:  Matt Newell, Public Works Director, 424-2747. Keith Alexander, Water Production Manager, 424-2863. Jennifer Gunter, Watershed and Lake Manager, 424-2834. Staff will be present at the Council meeting. 
BUDGET/TIME IMPLICATIONS:  These projects are funded by the Water Lake Capital Budget - Watershed Management. 
ATTACHMENTS:
DescriptionType
Resolution Authorizing Lake Decatur Watershed Protection Program Agreement for West Waterway Improvements with Lynn ClarksonResolution Letter